ČERNAY AGRO
Complex implementation of 100kWp photovoltaic system
Projection
Projection
Photovoltaic power plant with installed power of 99 kWpachieves annual solar gain of 109 MWh.
From the total annual consumption 1.274 MWhthe PV system will save 9 %
Total consumption of CO₂ emissions of volume 135.044 kgwill be reduced by 11.456 kg which represents the volume of emissions that has to be absorbed 572mature trees.
Annual electricity costs of 256.503 Eurare lowered by more than 23.777 Eur
Return of investment achieved 4 years.