ČERNAY AGRO
Complex implementation of 100kWp photovoltaic system
Projection
Projection
Photovoltaic power plant with installed power of 100 kWpachieves annual solar gain of 104 MWh.
From the total annual consumption 0 MWhthe PV system will save 48 %
Total consumption of CO₂ emissions of volume 13.392 kgwill be reduced by 6.433 kg which represents the volume of emissions that has to be absorbed 321mature trees.
Annual electricity costs of 26.784 Eurare lowered by more than 12.867 Eur
Return of investment achieved 5 years9 months.